- Competency Requirements
- Temporary works must be identified, coordinated/managed, designed and independently verified by appropriately qualified and approved persons appropriate to the level of the risk.
- A Temporary Works Category Evaluation must be completed to determine the appropriate experience of the Designer, Verifier and Site Validator.
- A competent person/s with relevant experience and qualifications must be appointed to undertake the duties of Temporary Works Coordination.
- Fit for Purpose Plant & Equipment
- Prior to using proprietary products, obtain specifications to understand its intended use and its compliance with applicable standards. Check if additional design and certification is required.
- Work Activity Requirements
Design Change Management
- The Project Manager and Project Engineering Manager must be consulted before proceeding with any changes to designs in the issued for construction stage.
- Temporary works changes must not occur without prior acceptance by the designer, and where required, completion of revised certification and independent verification.
Safety in Design (SID) Risk Assessment
- Planning and use of temporary works must be design risk assessed (Safety in Design) and conducted by competent persons with relevant experience and qualifications.