Design Reviews

  • A design review must be completed by the site worker responsible for the construction of the temporary works and other parties involved in the execution of temporary works.
  • The design must align with the project’s contractual obligations, all relevant laws and regulations, and applicable industry codes.
  • The design must be technically sound and fit for purpose.

 

Temporary Works Design Report

  • A Temporary Works Design Report must be in place and verified.
  • Ensure verification includes verifying the Temporary Works Design Report and any other design documents.
  • Ensure that all design documentation issued for construction, procurement, meets the necessary standards and requirements.

 

 

Design Verification & Validation

  • Temporary works must be regularly inspected by competent persons during installation, use, and dismantling.
  • Site Validation must be complete to inspect and confirm all temporary works have been constructed and/or fabricated in accordance with the design drawings and/or specification prior to its application. This includes temporary works that are erected directly on site, those that are prefabricated off site, and includes all temporary works installed by subcontractors / third parties.